So GW 2018.4 running on OES 2018.1 (Sles 12.3). Since the underlying server has been upgraded so many times, I would like to start with a fresh foundation. This kis a small system for a handful users.
The GW system is on a separate "disk" in the VM, so I thought I would do this:
1. Do alll the preliminary stuff., top-down rebuild, certificate checks etc.
2. Shut down agents and copy all GW files to an USB drive, copy or DBCopy
3. Shut down VM, back up the complete VM
4. Remove DS from the GW server
5. Clean up DS, removing all objects belonging to to the old server
6. Install a fresh 2024.x OES server with same name and IP
7. Attach the GW disk.
8. Install the GW agents
Have I missed anything? I remember when doing the 2018 upgrade that there was something quite inintuitive about installing the GW agents, but cannot remember what.