the screenshot below is from my task template, is there a way to kick off both of these processes at the same time, not wait for the 1st one to finish?
Cybersecurity
DevOps Cloud
IT Operations Cloud
If an answer to your question is correct, click on "Verify Answer" under the "More" button. The answer will now appear with a checkmark. Please be sure to always mark answers that resolve your issue as verified. Your fellow Community members will appreciate it!  Learn more
the screenshot below is from my task template, is there a way to kick off both of these processes at the same time, not wait for the 1st one to finish?
Yes! I believe the easiest way is to drag and drop one task on top of the other task. Both will become #1. It can be a little tricky to drop it in the right spot; a little too high and the task will be moved to the top, a little too low and the task will be moved to the bottom, but right in the middle and both will become task one.