• OOTB Time Approval Portlet

    Hi Etienne /Team, We have noticed that OOTB Time Approval Portlet only shows 5 rows by default. There is no indication of more rows in the portlet e..g Next button or total number of rows unlike other list portlets. More timesheets only show up only…
  • Can we hide or remove Expected Hours column on the timesheet

    Hi Team, Is there a way we can hide or remove "Expected Hours" column on the timesheet. This is not accurately maintained and we want to avoid user confusion.
  • Project Manager approval for zero hours against the project

    Hi Team, We have timesheet approval enabled for the Project Manager as and when time is charged to Project Tasks. What we have noticed is that PM's have to approve hours even if there are 0 hours charged against the tasks in the timesheets. Is there…
  • Efforts in the unsubmitted timesheet are shown in the project tasks.

    Hello, Quick question: Seems that, efforts in the unsubmitted timesheet are shown in the project tasks. Maybe I wrongly recalled but at least timesheet should be submitted to reflect and roll-up the efforts to the projects. Unfortunately, I could…
  • How to configure Summary Task Owner approver of his tasks only

    Hi All. I have a time policy based on Tasks where first level of Approvers are Summary Task Owners. In my understaing, any Summary Task Owner defined in the Work Plan can approve all tasks for all resources tracking time on the same Project. I have…
  • Add Custom Validation to Time Management Timesheet Entry Page

    I have a new PPM Time Management Time Sheet Entry Page Requirement that I believe is going to require major customization to the Time Sheet page and its associated processes. The new requirement is for each Request added to a time sheet, whenever a user…
  • HP PPM Time Management Estimates vs. Actuals

    We are using HP PPM version 9.22. We are creating Requests using Demand Management. I have set up Time Management Activities for all possible Request work items and have associated the Activities with appropriate Requests In the HP PPM Workbench, for…
  • PPM Support Tip: When Percent Complete is missing, update perc_complete in tm_work_units

    The follow are sql updates that were used to help some clients with such issues due to pre-9.14 Defects. When updating the Percent Complete, always update the Estimated Remaining Effort too, since they go together. -- update the percent complete from…
  • PPM Support Tip: Use 'Resource' "Group By" Field when running Actual Time Summary Report

    When running Actual Time Summary Report without 'Resource' "Group By" Field, Report returns a much larger Total Actual Cost than what is expected Time Management issue found in 9.21 - Use 'Resource' as a "Group By" filter The inconsistencies arise when…
  • PPM Support Tip: Delegate's Delegate could see Time Sheets to Approve

    A new KCS article was published: KM00672719. When Delegate's Delegate could see Time Sheets to Approve, error: "You do not have the privilege to take this action" Time Management issue found in 9.1 and fixed in 9.22 - items should not be appearing in…
  • PPM Support Tip: Project's Request Type User Access affects see it in a Time Sheet

    A new KCS article was published: KM00652933. When restricting access on a Project's Request Type, Resources in the Staffing Profile cannot see the Project in a Time Sheet Example: Mr.A and Mr.B belong to a Project Manager Security Group, though Mr. A…
  • Delete empty Time Sheet lines

    Hello, since 1.1.2013 we use Time Management in PPM. Before we started with time mgmt we activated the radio button in the time mgmt modul in the workbench: Allow the resource to submit a time sheet containing empty lines, with no warning . Now after…
  • PPM Support Tip: Delegating Project Manager privilege error when opening Time Sheet

    A new KCS article was published: KM00481635 When delegating from a Project Manager to another User, Delegated User gets a privilege error opening Time Sheet Time Management issue seen in 9.14 - "Evaluate TM Approvers Service" will not re-evaluate Delegate…
  • HP PPM Time Management Implementation

    Hello Community, I am working for an austrian bank and we are using HP PPM since March 2012, now version 9.13. Now we use Resource- and Demandmgmt moduls and put in master data in Project Mgmt modul (here we don't use Workplan, issue, risk,... yet). Our…