• update massive project type category for projects

    Hi All. I need to update massively the value of Work Load Category for all open projects of an existing Project Type Now the value is NULL and I want to set the value "Strategic Project" corresponding at SP for the field PM_PROJECT_TYPES.WORK_LOAD_CATEGORY_CODE…
  • Query for PPM Project Settings

    Hi everyone, May I ask if anyone has a sql select query for a list of PPM projects that has a specific settings For example, a list of Projects which has a Project Settings > Project Scheduling Integration > Integration Mode > Control is shared…
  • Can we disable the "Delete Work Plan" option for a Project Type

    Hi, Our customer wants the project manager to not be able to delete a work plan without actuals from their projects except for the PMO team. I checked the PPM documentation on the "Delete Work Plan" option and could not find anything that allow…
  • Search Projects By Project Type - PPM 9.66

    Hello All, We have created an Internal Project Request Type where access is set to our company security groups only, and our customer groups cannot see. We created a project type for these as well. In our testing with customer user accounts, we found…
  • Where is stored at project level to hide the Cost tab ?

    Hi All. After the upgrade at 9.66, the parameter HIDE_COST_TAB_ON_PROJECT_PAGE is no more working, replaced by the setting in the Project Overview Layout named "Show Cost Tab". In this phase I need to hide for all projects the Cost tab. Where this…
  • how to update project settings for a running project ?

    Hi All. Using PPM 9.22; PPM upgrade to 9.65 is scheduling. During the upgrade it is expected to remove a lot of custom code, replaced by OOTB capabilities. I need to modify the project settings, in particular the Project Overview Layout in order…
  • Project Participant (Assigned in Staffing Profile) not able to see Project Task in Timesheet

    HI, PPM Version : 9.41 Project settings: Project Security : Users who can view this project and its tasks: Only Participants Cost and Effort : Time Management : Track time at the : Task Level A user is allocated in a staffing profile line…
  • view delays in gantt view

    Hi All. I would like to highlight delays in the gantt view. Please see the screenshot coming from MS Projects: for each task I can see the scheduled period (the grey below) compared with the effective period (blue for completed task, red for non completed…
  • PPM Support Tip: Project Settings in a combination of tables

    When looking for Project Settings in the database, a combination of tables must be used. A client was trying to find the Project Settings for Projects in the schema. To find the settings for Projects, need the combination of the follow tables: PM_PROJECTS…
  • PPM Support Tip: Project's Request Type User Access affects see it in a Time Sheet

    A new KCS article was published: KM00652933. When restricting access on a Project's Request Type, Resources in the Staffing Profile cannot see the Project in a Time Sheet Example: Mr.A and Mr.B belong to a Project Manager Security Group, though Mr. A…