It would be great if additional options were added for Funding/Expense Types for “Exceptional” & “Hardware” in all modules associated with budgets in PPM. At the moment they seem to be limited to selecting only Capex or Opex and appearing as a selection…
This enhancement request is raised because of a staffing demand and allocation issue. The FTE values displayed in Team Management Utilization and Staffing Profile in some periods are sometimes different, while Hours and Person Days values are equal. …
By default PPM doesn't include request resource efforts inside staffing profiles. The unmet cell in the resource line in Staffing Profile page shows the capacity of assignments on SP. It does the calculation by including the assignments in all SPs and…
Can we please have a special command for copying staffing profile?
Link to discussion:
https://community.microfocus.com/adtd/sws-ppm/f/itrc-935/522457/special-command-to-copy-baseline-staffing-profiles
regards,
Ajay
We would like the ability to configure email notifications for when a project manager reduces the requested hours on a resource that has already been committed in a staffing profile. This notification should be sent to the resource manager and project…
When correcting or updating a project container's budget, it only allows whole dollars to be entered before applying it to the existing budget. This does not allow for fractional dollars to be adjusted. Can we have this configured to the hundredths, so…
HI Team, To ensure Project Managers have all the important information, can we include both Tasks and Region fields in the Staffing Profile extract? We noticed these fields are currently excluded when extracting data from the Staffing Profile. Thank you…
Hello,
We need to access some modules objects in rest api. There is no endpoint below objects. Could you please evaluate the endpoints ?
CRUD Resource Profile
Org Unit
Resource Pool
Resource Profile Informations
CRUD Staffing Profile…
Staffing Profile Cost to be updated on resource role change.
The cost in Staffing Profile only gets updated with a change in Staffing Profile.
Since the cost role is changing on the Resource Profile, no event seems to trigger the SP to update cost…
When the Start date of a project is moved forward, the staffing profile dates and the planning within the SP are moved forward as well. While it’s a nice feature, we have a customer who would not want to update the planned hours in the SP based on an…
The customer has raised that certain out of the box fields shown in the Statistics section of the Staffing Profile and the Summary section of the Financial Summary can be confusing if they don't use the field or call it something different. For example…
Current behaviour: When creating a Staffing Profile for a Proposal, the Staffing Profile region is populated with the default region as opposed to picking up the region from the Proposal. This happens automatically in projects. Request: The Staffing Profile…
When I want to export all the listed staffing profiles with their corresponding positions from the Forecast Planning page (Project Management > Staffing Profile > Manage Forecast), I am only able to export up to 1000 positions. This should be configurable…
When submitting a timesheet as a user on a team, the costs are coming through based upon the user's role cost rate, and not the team cost rate.
If we are forecasting dollars as a team, the actuals should come through in the same manner as well, Otherwise…
Ability to restrict the start and finish dates on the staffing profile & Financial Summary. Option : 1) Ability to lock the finish dates on staffing profile and financial summary. Also sync the dates with the associated parent. 2)